End-to-End Estimate Walkthrough
A complete worked example of building a small estimate from scratch. Follow it on a throwaway project; it ties everything in the guide together.
Scenario
You've been asked to price a small concrete slab extension:
- 100 m² of 150 mm reinforced slab.
- 30 linear metres of formwork edge.
- Steel reinforcement mesh.
- Four weeks on site.
Step 1 — Create the Project
- Projects → New Project.
- Name: "Slab Extension Example".
- Currency: AUD.
- Tax: 10%.
- Create.
Step 2 — Create Resources
Go to Resources and create:
| Name | Type | Unit | BaseRate |
|---|---|---|---|
| Concrete 25MPa | Material | m³ | $180 |
| Reinforcement mesh SL82 | Material | m² | $18 |
| Formwork timber | Material | m | $14 |
| Labourer | Labour | hr | $62 |
| Concreter | Labour | hr | $78 |
| Concrete pump | Plant | hr | $140 |
Step 3 — Enter Direct Costs
Go to Direct Costs. Add parent header rows and child items:
1 Slab Extension
2 Concrete supply Qty 15 m³ Concrete 25MPa → $2,700
3 Reinforcement Qty 100 m² Mesh SL82 → $1,800
4 Formwork edge Qty 30 m Formwork timber → $420
5 Place and finish Qty 24 hr Concreter → $1,872
6 Concrete pump hire Qty 3 hr Concrete pump → $420
Select rows 2–6 and press Tab to indent under row 1. Row 1 becomes a header; its TotalWithChildren = $7,212.
Step 4 — Use a Formula
Line 2 quantity should be volume: 100 m² × 0.15 m = 15 m³. Replace the typed 15 with:
Qty: = 100 * 0.15
Or add a project parametric #slab_area = 100 and #slab_depth = 0.15, then Qty: = #slab_area * #slab_depth. Now changing #slab_area re-prices automatically.
Step 5 — Add a Breakdown
Select line 5 ("Place and finish"). Press Ctrl+B to open breakdowns. Add:
L1 Concreter Qty 3 × 8 hr Concreter → $1,872
L2 Helper Qty 3 × 8 hr Labourer → $1,488
Parent total becomes $3,360. The breakdown shows line-level detail behind the single parent row.
Step 6 — Enter Overheads
Go to Overheads. Add:
| Item | Qty | Unit | Resource / Rate | Total |
|---|---|---|---|---|
| Site supervisor | 4 | wk | $3,500 | $14,000 |
| Temporary fencing | 1 | lump | $1,800 | $1,800 |
| Insurance & bonds | 1 | lump | $2,500 | $2,500 |
Overhead pool = $18,300.
Step 7 — Set Markup and Margins
Markup → Configure:
- Labour markup 20%.
- Material markup 10%.
- Plant markup 15%.
- Risk margin 5%.
- Corporate overhead 4%.
- Profit margin 10%.
Click Recalculate.
Step 8 — Check the Sell Rates
Open Sell Rates. Each direct cost line now shows:
| Line | Direct | Allocated OH | Markup | Margins | Sell Total | Factor |
|---|---|---|---|---|---|---|
| Concrete supply | $2,700 | $1,670 | ~$437 | ~$689 | ≈ $5,496 | 2.04 |
| Reinforcement | $1,800 | $1,113 | ~$291 | ~$460 | ≈ $3,664 | 2.04 |
| Formwork edge | $420 | $260 | ~$68 | ~$107 | ≈ $855 | 2.04 |
| Place & finish | $3,360 | $2,078 | ~$1,087 | ~$1,330 | ≈ $7,855 | 2.34 |
| Pump hire | $420 | $260 | ~$102 | ~$125 | ≈ $907 | 2.16 |
(Figures approximate; exact values depend on proportional distribution.)
Total sell = ≈ $18,777. Margin ≈ 40%.
Step 9 — Carbon
Go to Carbon. Click Auto-populate from resources. Emissions appear for each line:
Concrete 25MPa 15 m³ × 240 kgCO₂e/m³ = 3,600 kgCO₂e (Scope 3)
Mesh SL82 100 m² × 4.5 kgCO₂e/m² = 450 kgCO₂e (Scope 3)
Formwork timber 30 m × 2 kgCO₂e/m = 60 kgCO₂e (Scope 3)
Labour on-site + diesel (Scope 1) = 400 kgCO₂e (Scope 1)
Total ≈ 4.5 tCO₂e, 91% Scope 3.
Step 10 — Save a Snapshot
Carbon → Save Snapshot → note: "Tender submission".
Step 11 — PDF Report
Reports → Generate Project Summary PDF. Tick all sections, set Company Name and logo. Save. Send to client.
Step 12 — Archive
Once complete, set Project Status = Completed. Export a .tx1 file as a backup.
Recap
You have exercised:
- Projects (02), Resources (03), Direct Costs (04), Overheads (05), Markup / Sell Rates (06), Formulas (07), Carbon (09), Reports (12), and export (13).
Every larger estimate is this pattern at greater scale.